Uptown Transportation Improvements

Share on Facebook Share on Twitter Share on Linkedin Email this link

Project Update 3/6/24: This Project is going to construction! The construction contract has been awarded to Argenio Bros of New Windsor, NY. Tree Removal is planned for March 2024, with full mobilization planned for May 2024. Additional updates will be provided as work begins.

Project Background: With funding provided by the Downtown Revitalization Initiative (DRI), administered by the NYS Department of State, the City will improve safety and traffic circulation on a route in Uptown Kingson / Stockade Business District.

The Uptown Transportation Improvements Project will address bicycle and pedestrian safety and access, capacity, and attract tourism, shopping, dining, and business activity to the Stockade District. It will also support the future connection between portions of the Kingston Greenline and advance complete streets across the City (see FAQs for more info).

The project is focused on improvements to Clinton Avenue between Westbrook Lane, Main/John Street, and Albany Avenue.

Work will include lane narrowing, sidewalk and curb ramp improvements, a new signal at the intersection of Clinton and Westbrook / John, signage, striping, landscaping, lighting, drainage and access management improvements.

Since early 2020, our Project Advisory Committee (PAC) has been assisting in the decision-making process about the design. The group provided a wide range of concerns and ideas and the City and HVEA conducted a traffic analysis to inform the development of design alternatives.

The City also partnered with Susan G. Blickstein, LLC, a transportation policy and public engagement firm, which developed two community surveys that were open from May 7 through June 15 2020. The surveys were designed to collect information about how community members travel along the routes, their perceptions about safety, and the preferred types of improvements they would like to see. Results of the public surveys are posted to the right.

The PAC and City staff considered eight different alternatives and narrowed those down to one priority recommendation. This alternative was presented in a virtual public meeting on November 19, 2020. Links to recordings of the presentation in English and in Spanish are also posted to the right.






Please add your comments to Share Your Thoughts below. Further information about our selection process can be found under Design Process. Public Comment will be open on this project through September 1, 2023.


●●●


Project Update 3/6/24: This Project is going to construction! The construction contract has been awarded to Argenio Bros of New Windsor, NY. Tree Removal is planned for March 2024, with full mobilization planned for May 2024. Additional updates will be provided as work begins.

Project Background: With funding provided by the Downtown Revitalization Initiative (DRI), administered by the NYS Department of State, the City will improve safety and traffic circulation on a route in Uptown Kingson / Stockade Business District.

The Uptown Transportation Improvements Project will address bicycle and pedestrian safety and access, capacity, and attract tourism, shopping, dining, and business activity to the Stockade District. It will also support the future connection between portions of the Kingston Greenline and advance complete streets across the City (see FAQs for more info).

The project is focused on improvements to Clinton Avenue between Westbrook Lane, Main/John Street, and Albany Avenue.

Work will include lane narrowing, sidewalk and curb ramp improvements, a new signal at the intersection of Clinton and Westbrook / John, signage, striping, landscaping, lighting, drainage and access management improvements.

Since early 2020, our Project Advisory Committee (PAC) has been assisting in the decision-making process about the design. The group provided a wide range of concerns and ideas and the City and HVEA conducted a traffic analysis to inform the development of design alternatives.

The City also partnered with Susan G. Blickstein, LLC, a transportation policy and public engagement firm, which developed two community surveys that were open from May 7 through June 15 2020. The surveys were designed to collect information about how community members travel along the routes, their perceptions about safety, and the preferred types of improvements they would like to see. Results of the public surveys are posted to the right.

The PAC and City staff considered eight different alternatives and narrowed those down to one priority recommendation. This alternative was presented in a virtual public meeting on November 19, 2020. Links to recordings of the presentation in English and in Spanish are also posted to the right.






Please add your comments to Share Your Thoughts below. Further information about our selection process can be found under Design Process. Public Comment will be open on this project through September 1, 2023.


●●●


Schwenk Drive and Clinton Avenue FinalDesigns

To provide any comments and feedback for the design concepts of Schwenk Drive and Clinton Avenue, please go to the SHARE YOUR THOUGHTS tab. 

SCHWENK DRIVE

A larger scope of work was initially planned for Schwenk Drive, however due to funding limitations, as well as the need to acquire right-of-way, including railroad tracks, the project scope on Schwenk Drive was reduced to including only signage and striping improvements at the intersection of Schwenk and Plaza Drive / Fair Street Extension.  The current non-functioning traffic signal will be removed.  The final plan is shown below:






CLINTON AVENUE

Excerpts from the final plans are presented below:

1. Striping Plans, Clinton Avenue:




2. Signal Plans, Clinton at Albany (replacement signal)

3. Signal Plan, Clinton at John / Westbrook (new signal)

Please share your comments and feedback in the SHARE YOUR THOUGHTS tab. If you have a story that you want to share about Schwenk Drive and Clinton Ave. that you want to share, feel free to share below as well. Thank you! 



You need to be signed in to share your story.

All fields marked with an asterisk (*) are required.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Please don't sacrifice cyclist safety on Schwenk Drive

    by EzLynn, 6 months ago
    I'm very sad to see the scope of the Schwenk Drive project has been narrowed so drastically. I really hope the City will still do something to increase safety for cyclists on this street and that in the imminent future that can include a protected bike lane. We have 5 lanes for cars and nothing for our most vulnerable road users :-(
  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Taking out crosswalks is a mistake

    by Smwenk, 8 months ago
    Removing the crosswalks at Main crossing Clinton is a terrible idea. Forcing pedestrians to walk to another corner to cross is punitive and belittling, it privileges cars, as does so much of Kingston's infrastructure. Removing these crosswalks will just make drivers go faster and reduce safety for everyone else. Also, why don't the ADA ramps line up with the crosswalks??



Page last updated: 06 Mar 2024, 11:52 AM